Bridge to Permanent: What to Line Up Before Completion

Construction closing gets the attention because it is where the money moves. Conversion is where deals get hurt, because by then the contingency is spent and the options have narrowed.

The tests that have to clear

Permanent loan conversion usually turns on a small number of conditions, and every one of them is measurable long before you reach it. Physical completion and certificate of occupancy. A debt service coverage test measured over a stated period of actual operations, commonly ninety days, sometimes longer. An occupancy threshold. Lien free completion with final contractor releases. Cost certification. And on a credit deal, the placed in service date and the 8609 process behind it.

Pull those conditions out of the loan documents at construction closing and put them on a single page with dates. Most conversion failures are a condition nobody was tracking.

Lease up is an underwriting assumption, not a formality

The coverage test is measured on actual collections, and actual collections on an affordable property depend on certification throughput, not on demand. There is usually a waiting list. Whether the units get occupied on schedule depends on how fast the management agent can process income certifications correctly, and on whether the voucher administrator's inspections keep pace.

Staff the certification function before the first unit is ready and audit the first twenty files yourself. A file error found in month two is a correction. The same error found at the coverage test is a failed test.

The equity installment and the timing hole

The final equity installment commonly arrives at stabilization or at receipt of 8609s, and those are not the same date as permanent conversion. Between the last construction draw and the last equity dollar there is often a window where the deal needs money it does not have. That is what a bridge is for, and it should be sized and committed at construction closing rather than arranged under pressure.

The cost of a short bridge that was planned is small. The cost of an unplanned one, negotiated when the lender knows you have no alternative, is not.

What we check at the ninety day mark before completion

Final contractor documentation and lien waiver status. Cost certification engagement underway, not scheduled. Certification files audited. Reserve funding confirmed against the permanent lender's requirement, which is often larger than the construction lender's. Insurance converted to permanent form. The investor's checklist for the final installment, item by item, with an owner for each item.

None of this is interesting. All of it is cheaper to do early.

Topics: construction to permanent conversion, LIHTC stabilization, bridge loan affordable housing, permanent loan conversion conditions, 8609
← All insights

Talk through a specific deal

Send the site, the subsidy you are pursuing and the number you think the gap is. We will tell you what we would do next.

Start a project inquiry →